How much MOT Type 1 do I need for a driveway?
Multiply the driveway area by the sub-base depth. A 10 m × 3 m driveway with a 150 mm MOT Type 1 sub-base needs about 4.5 m³ - roughly 9 tonnes, as Type 1 compacts to around 2 tonnes per cubic metre. Enter your size and depth above. Remember the sub-base is a separate layer under the surface gravel, tarmac or block paving.